East Train Platform Reconstruction

Posted on: April 30, 2018

East Platform - May Work Schedule

East Platform reconstruction work is scheduled to officially recommence beginning May 1, and major structural work should be completed by June 1 pending weather or railway operational conditions. The north and south platforms will remain open with no anticipated disruption to commuter use. 

The following work is anticipated to take place during May

  • Curb and gutter
  • Precast capstone
  • Landscaping and sidewalk
  • Ornamental handrail
  • Sidewalk
  • HMA pavement patching
  • Brick pavers

The following work is anticipated to take place during June

  • Irrigation
  • Final landscaping
  • Site furnishings
  • Electrical
  • Pavement markings