Road Construction Projects

Posted on: November 21, 2018

2018 Roadway Program - Johnson Avenue/Lawn Avenue Driveway Access

Johnson Avenue 

Driveway access to the west side of Johnson Avenue (45th-46th) will be available on 11/23/18. Once the west lane is opened, vehicles will be available to enter and exit the block at the 46th and 45th Street intersections. The contractor will be  present on Friday and Saturday prepping and pouring the sidewalks at all intersections, and the west intersection of 46th Street, weather permitting.

Lawn Avenue

Driveway access on the west side of Lawn Avenue has been re-opened for use. Please keep in mind that Lawn Avenue itself may be partially closed during construction hours to allow the contractor access to the remaining work. The contractor is scheduled to pour the west sidewalk on Saturday and Monday, weather permitting. 

Please contact Casey Biernacki at 708-246-1800 x 276 or at cbiernacki@wsprings.com with any questions or concerns.