Road Construction Projects

Posted on: May 24, 2019

2018/2019 Roadway Programs - Status Updates

2018 Roadway Program

The consistent rainfall continues to delay the procurement of the topsoil required for the project. The Chicago-land area is reaching record high rainfall this spring, which is halted topsoil production throughout the state. Topsoil requires consistent dry days to be created and distributed in the volume required for this project.  The landscaper is scheduled to arrive on Johnson and Lawn the moment topsoil is available for purchase. 

2019 Roadway Program

Staff met with DiNatale Construction, the general contractor, today for the pre-construction meeting. The Village is still awaiting final approval of the contract from the Illinois Environmental Protection Agency (IEPA). Once approved by the IEPA, the contractor and the Village can sign the contracts and work can commence. DiNatale is tentatively scheduling to start the project in mid-June, pending the IEPA approvals. 

If you have any questions or concerns, please contact Casey Biernacki at 708-246-1800 x 276 or at cbiernacki@wsprings.com. 


Facebook Twitter Email