Road Construction Projects

Posted on: August 6, 2019

2019 Roadway Program - Clausen Possible Water Service Interruption on 8/9/19

The contractor will begin connecting the new 8" water main to the existing water system on August 8, 2019, weather permitting. The first connection will take place at 41st and Clausen. The work is intended to be performed without interrupting service for residents on Clausen Avenue. However, it is always possible additional water shut downs will need to take place in order to isolate the area and allow the work to occur. Please be prepared for a possible interruption in water service on Clausen Avenue, beginning at 9:00AM on Thursday morning. The work is tentatively scheduled to take 4-5 hours. 

Please contact Casey Biernacki at 708-246-1800 x 276 or at cbiernacki@wsprings.com