Road Construction Projects

Posted on: August 23, 2019

2019 Roadway Program - Pavement Removal Beginning on Clausen on 9/3/19

The underground sewer and water main work on Clausen is tentatively scheduled to be completed during the first week of September. The contractor is scheduled to begin pavement removal of the east lane of Clausen Avenue on September 3, 2019, weather permitting. Completion of the underground work may dictate if the contractor begins on the north end of Clausen, at 39th, or at the south end, at 41st. A future update will specify the exact location that pavement removal will begin. 

Once pavement removal starts, residents on the east side of Clausen will lose access to their driveway for 3-4 weeks. All residents will be allowed to park on the surrounding side streets over night while your driveway is inaccessible. Temporary handicap parking will be available at the first on-street parking space at each intersection. Please visit the project web page at http://www.wsprings.com/534/2019-Roadway-Referendum-Project to view maps of all on-street parking locations. The west lane of Clausen Avenue will remain open as a one-way street, northbound. Please remember that access to the west lane may be difficult during working hours as heavy machinery and workers will be on-site. 

Please contact Casey Biernacki at 708-246-1800 x 276 or at cbiernacki@wsprings.com with any questions or concerns.