Road Construction Projects

Posted on: September 16, 2019

2019 Roadway Program - Clausen East Lane Update/Lawn Avenue Schedule

The contractor is completing the installation of the new roadway base for the east lane of Clausen this week. They intend to get the east lane curb and driveway aprons installed this week if the weather cooperates. They will then pour the east driving lane, which will be left to cure for 7-10 days. The contractor cannot work on the west side of Clausen until the curing process is completed.

When the east lane is curing, the contractor is planning to move their crews to the east lane of Lawn Avenue to begin removal of the pavement. A definitive date for the Lawn Avenue east lane removal is not set, but future updates will provide that information. The removal of the east lane of Lawn Avenue is estimated to occur at the end of September. 

Please contact Casey Biernacki with any questions or concerns.

Facebook Twitter Email

Other News in Road Construction Projects

Leaf Pick-Up During Roadway Projects

Posted on: October 21, 2019