Lawn Avenue Reconstruction Part 2 - Temporary Changes in Traffic Flow

Lawn Avenue Traffic - Round 2 copy

Beginning October 15, the west lane of Lawn Avenue (Elm Street to 47th) will be removed and replaced, weather permitting. The replacement process is estimated to take 2-3 weeks.

The east lane of Lawn Avenue will remain open for use as a one-way, southbound street after construction hours and on the weekends. 

Vehicles may enter Lawn Avenue, southbound, from Burlington Avenue to access businesses and the Post Office.  Post Office Drive is available as a detour for anyone heading southbound on Lawn. 

Elm Street will undergo periods of time when east/west access is unavailable. Please respect and observe all construction barriers. 

Attached is a flyer that shows a graphic depiction of these temporary changes. 

Contact Casey Biernacki at 708-246-1800, ext. 276 or cbiernacki@wsprings.com with any questions or concerns. 