Road Construction Projects

Posted on: October 9, 2019

2019 Roadway Improvements - Lawn Avenue (47th to Elm) West Lane Start Date

The west lane of Lawn Avenue (47th to Elm) is tentatively scheduled to be removed on Tuesday, October 15, 2019. The actual start date heavily depends on the concrete testing results from the east lane. Tests results for the east lane will be received on October 14th, 7 days after the last concrete pour. If the results are positive, the east lane of Lawn will be re-opened on October 14th with construction on the west lane beginning the next day. Another update will be sent out on Monday once the results are received. 

Please contact Casey Biernacki at 708-246-1800 x 276 or at cbiernacki@wsprings.com with any questions or concerns.