Posted on: July 19, 2017

2017 Roadway Program - East Lane Removal Rescheduled to Monday, July 24th Due to Weather

G&M Cement will begin removal of the east lanes on Monday, July 24th, weather permitting.  Work will begin at 39th St. and Harvey avenue and move south towards 41st Street.

Please note that the start has been changed due to impending inclement...

Read on...

Road Construction Projects
Posted on: July 18, 2017

2017 Roadway Program - Official Start Date

Official Start Date

The official start date for the roadway portion of the project will begin on July 20, 2017, at 7:30 AM, weather permitting. Bad weather will result in a delay to the start date until the next available working day.  The contrac...

Read on...

Road Construction Projects
Posted on: July 14, 2017

2017 Roadway Program - Construction Update and Temporary Change in Contact Info

Construction Update

The storms earlier this week delayed the contractor from beginning the saw cutting and excavation of the east lane of Howard and Harvey Avenue. We require at least 24 hours of notice from the contractor before excavation work can begin ...

Read on...

Road Construction Projects
Posted on: July 7, 2017

2017 Roadway Program - East Lane Construction Start Date Reminder

G&M Cement is planning to begin construction of the east lanes of Harvey and Howard during the middle next week, weather permitting.   A construction update will be sent out at least 24 hours ahead of time so please continue to check your e-m...

Read on...

Road Construction Projects
Posted on: June 23, 2017

2017 Roadway Program - Construction Update and Golf Cart Information

Construction Progress Update

The underground contractor has completed all sewer work included in Phase 1 of the project.  Phase 2, the reconstruction of the east lane of both Howard and Harvey, has been delayed until the week of July 10, 2017. &am...

Read on...

Road Construction Projects
Posted on: June 13, 2017

2017 Roadway Program - Sewer Installation Update

Construction Update

The contractor has completed the major sewer work on the 4000 block of Harvey Avenue.  They will continue north today to work on various sanitary and drainage structures.  Residents of Howard Avenue (47th-48th) should ...

Read on...

Road Construction Projects
Posted on: May 30, 2017

2017 Roadway Program - Start Date Delayed

The start date for the 2017 Roadway Program has been delayed until June 5, 2017.  The contractor plans to begin underground sewer work at the corner of 41st Street and Harvey Avenue.  Access to Harvey Avenue will remain open for the majo...

Read on...

Road Construction Projects
Posted on: May 22, 2017

2017 Roadway Program - Official Schedule and Updates

Project Schedule

The official project schedule has been received from G&M Cement.  The schedule may change due to weather or unforeseen circumstances during construction.  The schedule is as follow:

May 30th - June 16th: All sewer work...

Read on...

Road Construction Projects