News Flash

Posted on: December 10, 2018

2018 Roadway Program - Substantial Completion and Full Access

The 2018 Roadway Program is substantially complete and both Lawn Avenue and Johnson Avenue will be fully open for public use today. The parkways have been regraded for the winter and fresh topsoil and sod will be installed in the spring. Another update wi...

Read on...

Road Construction Projects
Posted on: November 30, 2018

2018 Roadway Program - Johnson Avenue Access (Update 11/30/18)

Please refer to the list below on available access to Johnson. Additional updates will be sent out as access changes. Please remember that all dates are weather dependent. 

Johnson/45th

The sewer contractor has completed all work at the intersectio...

Read on...

Road Construction Projects
Posted on: November 29, 2018

2018 Roadway Program - Johnson Avenue Access

There are multiple contractors on-site performing work on Johnson Avenue. Please refer to the list below on available access to Johnson. Additional updates will be sent out as access changes. Please remember that all dates are weather dependent.

Johnson/4...

Read on...

Road Construction Projects
Posted on: November 28, 2018

2018 Roadway Program - Project Update 11/28/2018

Lawn Avenue

The contractor will be on-site tomorrow morning to the pour the remaining west sidewalk and any miscellaneous sidewalk on Lawn. The contractor will then focus on filling in all brick paver areas for the winter as they will be installed in the s...

Read on...

Road Construction Projects
Posted on: November 21, 2018

2018 Roadway Program - Johnson Avenue/Lawn Avenue Driveway Access

Johnson Avenue 

Driveway access to the west side of Johnson Avenue (45th-46th) will be available on 11/23/18. Once the west lane is opened, vehicles will be available to enter and exit the block at the 46th and 45th Street intersections. The contr...

Read on...

Road Construction Projects
Posted on: November 14, 2018

2018 Roadway Program - Saturday Work

The contractor has requested the ability to work on the remaining Saturdays this year. The Municipal Code states that heavy machinery cannot be used between the hours of 9:00AM-5:00PM on Saturdays (5-2-3 Limitations of Construction Noise). The contractor ...

Read on...

Road Construction Projects
Posted on: November 14, 2018

Johnson Avenue Intersection Closures/Johnson Avenue (46th-45th) Access (Updated 11/16/2018)

Update 11/16/2018

Please refer to the updated Intersection Closure Map. The intersection work has been re-configured due to the ComED utility poles. The poles in questions are scheduled for removal today, but their presence has delayed a the west portion o...

Read on...

Road Construction Projects
Posted on: November 12, 2018

2018 Roadway Program - Project Update 11/12/2018

The contractor is preparing the sub-base of both Lawn Avenue and Johnson Avenue (45th-46th) and pouring some driveway apron and curb gaps today and tomorrow. The west lane of Lawn Avenue is scheduled to be poured on Wednesday, November 14, 2018. Additiona...

Read on...

Road Construction Projects
Posted on: November 7, 2018

2018 Roadway Program - Project Update 11/7/2018

The contractor is still on schedule to complete the majority of the concrete items (pavement, driveways, sidewalk, etc.) by the Thanksgiving Holiday. All landscaping items (restoration of parkway with sod, tree/landscaping plantings, etc.) will likely be ...

Read on...

Road Construction Projects
Posted on: October 30, 2018

2018 Roadway Program - West Johnson Avenue (46th-45th) Removal Start Date

The contractor will begin pavement removal on the west lane of Johnson (45th-46th) as early as tomorrow morning. All residents on the west side of Johnson Avenue (45th-46th) should have your vehicles out of your driveway by 7:00AM tomorrow (10/31/18) morn...

Read on...

Road Construction Projects
Posted on: October 26, 2018

2018 Roadway Program - East Lane of Johnson Avenue (45th-46th) Re-Opening

The east lane of Johnson Avenue (45th-46th) is scheduled to be re-opened today, pending the final concrete test results. If the lane is not re-opened today, it will be re-opened on Monday morning. The contractor will remove barricades from driveway aprons...

Read on...

Road Construction Projects
Posted on: October 25, 2018

2018 Roadway Program - Nicor Gas Main Conflict on Lawn Avenue

The contractor has discovered a very shallow 2" Nicor gas main on Lawn Avenue. The main in question was displayed on the plans and specifications, but its depth was shallower than the standard depth for Nicor. Village staff and the contractor are wor...

Read on...

Road Construction Projects
Posted on: October 22, 2018

2018 Roadway Program - Leaf Pick-Up

Leaf pick-up will remain available on Johnson Avenue and Lawn Avenue. Please pile your leaves on the parkway, between the sidewalk and curb. Public Works crews will retrieve them with the vactor truck if the roadway is available. If they cannot get down t...

Read on...

Road Construction Projects
Posted on: October 16, 2018

2018 Roadway Program - West Lawn Avenue Pavement Removal Start Date

The contractor will begin the removal of the west lane of Lawn Avenue tomorrow, October 17, 2018, weather permitting. Residents on the west side of Lawn should have your vehicles our of the driveway by 7:00 AM. Vehicles are allowed to park overnight on th...

Read on...

Road Construction Projects
Posted on: October 8, 2018

2018 Roadway Program - Johnson Avenue Sewer Information

Staff has received various correspondences today. Please see the information below to help clear some of the misinformation.

Storm Sewer Installation 

Johnson Avenue was previously comprised of a single sewer (varying between 10"-12") ben...

Read on...

Road Construction Projects