News Flash

Posted on: August 14, 2019

Well 5 Drilling: 08/14/19 Weekly Project Update

Drilling of the 23” borehole continues this week. Next week activities will continue with single shift operations. 


    

Well 5 Construction
Posted on: August 5, 2019

Well 5 Drilling: 08/05/19 Weekly Project Update

Layne returned to site and put together 23” tooling after allowing cement to continue to cure on Monday, July 28th. Drilling resumed on Tuesday, July 29th and cement was drilled out of hole and continued with rock drilling to a depth of 105 feet...

Read on...

Well 5 Construction
Posted on: July 29, 2019

Well 5 Drilling: 07/29/19 Weekly Project Update

Layne completed the drilling of the upper borehole and installation of 24' casing to a depth of 39 ft and cemented casing on Friday. Cement will allowed to cure over weekend and today.

This week's activities will include installation of tooling into the ho...

Read on...

Well 5 Construction
Posted on: July 25, 2019

Well 5 Transmission Main: Start Date Scheduled for July 29th

Swallow Construction is scheduled to begin the mechanical bore for the new transmission main beginning Monday, July 29th. The new transmission main will be installed along the south curb line on Hillgrove Avenue from Johnson Avenue to Ellington Avenue. Pa...

Read on...

Well 5 Construction
Posted on: July 22, 2019

Well 5 Drilling: 07/22/19 Weekly Project Update

Site security fencing was installed on Tuesday, July 16 and Layne-Christensen mobilized all drilling equipment to site.

Layne-Christensen  will continue with rigging up of equipment and will begin mixing drilling mud and starting of the 30” boreho...

Read on...

Well 5 Construction