Well 5 Construction
-
Well 5 Drilling: 11/01/19 Weekly Project Update
Well crews have completed the 24-hr. test pumping last week. Read on...
Overview
The Village is implementing a water infrastructure improvement plan, utilizing a low interest loan from the IEPA's revolving loan program. The construction of a new deep well for the Village's water supply has been approved by the Village Board and is scheduled for construction in 2019. The Village has secured funds for the construction of the well through the IEPA.
Construction Updates & "Notify Me"
One of the most important aspects of a successful roadway project is communication with residents. Construction updates will be posted in the "News Flash" section on the right side of this page. These updates will contain information pertaining to the construction schedule, anticipated changes to the project and any additional progress updates.
To sign up to receive weekly updates in an e-mail and/or text message, follow the steps below.
- Click on "Stay Informed" on the left side of this page.
- Enter your e-mail address in the text box at the top of the page and click "Sign In".
- Scroll down to the "News Flash" section of the page and click the
next to "Well No 5 Construction".
- Optional: If you would like to also receive text message updates, first select the check box below your e-mail next to "I would like to be able to receive text messages on my mobile phone". Then click the
next to Road Construction Projects.
The project will begin late fall, early winter of 2018 with the replacement of approximately 100' of sanitary main running north-south through Field Park. The sanitary main adjacent to the proposed well site will be upgraded to potable water quality pipe.
Construction of the new well will begin with the drilling and will commence around July 2019. Drilling is expected to take approximately four months. During this period some overnight work may be required. The "Typical Deep Rotary" drill rig setup consists of the following equipment
- Drill Rig
- Dog House
- Crane
- Drill Pipe Trailer
- Pump #1 & #2
- Mud System
- Generator
- Dog House
The new well will facilitate the need for a new transmission main to run from Field Park, east to the Water Treatment Plant located near Johnson Avenue and Hillgrove Avenue. The transmission main work is expected to occur concurrently with the drilling of the new well. Work is anticipated to begin around July 2019 and take approximately 4-6 weeks.
The new main will be mechanically bored near the southern curb line of Hillgrove Avenue. Parking along the south side of Hillgrove Avenue will be temporarily closed while boring is occuring.
Once the drilling of the well is complete, the well pumping equipment and electrical systems will be installed. Work is anticipated to commence during the fall of 2019. The final well site will include a pit-less well design with a small building for the electrical equipment on the site.
-
Matthew Supert
Director of Municipal Services
-
Erin Duffy
Water Plant Superintendent
Proposed Project Area
The new well will be constructed in existing Village Right of Way located south of the Ellington Avenue cul-de-sac near Hillgrove Avenue.