Restoration of Well #3 was completed on 06/02 and has been put back into service. Watering restrictions have been lifted.
Reinsertion of the pump and motor was completed the week of 05/15. Additional electrical work was conducted through last week, including the replacement of a transformer by ComED on the utility pole adjacent to the well. Village staff began flushing the well to waste on 05/24.
Some additional repairs to the lighting suppression system and controls system are still required. Well #3 will be chlorinated and run to the reservoir on a supplemental basis. Well #4 will continue to be softened through the RO plant.
Hardness and iron levels in the distribution system should decrease over the next several days.