News Flash Home
The original item was published from 7/29/2019 8:14:13 AM to 9/3/2019 12:00:10 AM.

News Flash

Well 5 Construction

Posted on: July 29, 2019

[ARCHIVED] Well 5 Drilling: 07/29/19 Weekly Project Update

Layne completed the drilling of the upper borehole and installation of 24' casing to a depth of 39 ft and cemented casing on Friday. Cement will allowed to cure over weekend and today.

This week's activities will include installation of tooling into the hole and beginning of drilling of 23' of borehole. Due to shift break needed on drillers, no work is planned to be performed on Thursday/Friday of this week.

Facebook Twitter Email