[ARCHIVED] Well 5 Drilling: 08/05/19 Weekly Project Update

Layne returned to site and put together 23” tooling after allowing cement to continue to cure on Monday, July 28th. Drilling resumed on Tuesday, July 29th and cement was drilled out of hole and continued with rock drilling to a depth of 105 feet on Friday, August 2nd, prior to weekend break.

This week activities continued with single shift operations while second driller is brought in to get comfortable with operations. We will continue to work in the background to get a position to go to 24 hr operations for the next phase of the drilling operations. 

                                                       


    