Well 5 Construction

Posted on: August 27, 2019

[ARCHIVED] Well 5 Drilling: 8/27/19 Weekly Project Update

Drilling of the 23" borehole continues and crews have achieved 575' on 08/23/19.

Starting Monday. 08/26/19  Layne will run 24 hour shifts until Thursday.  Layne has a mandatory shutdown of all field crews on Friday for safety training.  Work will resume again on Saturday through Sunday.  No field work will occur on Labor day.    