Well 5 Construction

Posted on: September 13, 2019

[ARCHIVED] Well 5 Drilling: 9/13/19 Weekly Project Update

Casing was installed circulation was re-established prior to cementing. Casing was cemented on Tuesday and will be left to cure until noon on Friday. Crew will begin drilling out any cement and cement shoe over the weekend. Once cement is drilled we will switch over to the reverse drilling and resume.

Drilling of production hole over the weekend to a target depth of 1,550 ft. This could be reached by Monday or Tuesday of next week. Once target depth is reached, some development will occur by air lifting of the hole to clean up the production water. Once cleaned up, drill tooling will be removed, and site demobilization will begin.