Well 5 Construction

Posted on: September 24, 2019

[ARCHIVED] Well 5 Drilling: 9/24/19 Weekly Project Update

Drilling has reached a total depth of 1,535 feet and drilling work has completed. Layne crews began removing equipment at the end of last week and will begin transitioning to test pumping equipment. Test pumping is anticipated to begin the week of October 7th. 

All work will resume with a single shift until 24-hr testing is required. 