[ARCHIVED] Well 5 Drilling: 11/01/19 Weekly Project Update

Well crews have completed the 24-hr. test pumping last week. The test was run at 1,331 gpm. Water quality sampling is expected to be completed by mid-November. The Village is currently out to bid with the well pumping equipment and those bids will open on December 5, 2019.