Rose/Grove Roadway and Water Main Improvements

Posted on: September 24, 2021

Rose/Grove project schedule update 9/23

The Village is expecting project work to begin the week of 9/27. The first work item is water main installation on Grove between Chestnut and Maple. 

The Village has mailed a project update to residents on Rose and Grove. The project update includes the anticipated construction timeframes for each block of the project. The letter can be viewed by clicking here