Please find a project update letter dated 11/8/21 at this link: 11-8-21 Rose-Grove Update letter
Work anticipated this week and next week:
This week the contractor expects to work on sewer inlet and pipe replacements at the intersections of Rose & Oak, Rose & Grove, and Maple & Grove. Next week the contractor is expected to complete water service line installations on Rose.