Work Completed the week of 4/25:
The Contractor (A Lamp) completed removal of the old pavement and placement of the stone base course for the new pavement on Grove Avenue between Chestnut & Oak as well as on the west side of Rose. They also removed old driveway aprons on the west side and placed the new concrete aprons on Grove between Chestnut and Oak. A majority of concrete pavement was placed on the west side of Grove between Ogden and Chestnut except for a couple locations where underground utility repairs had delayed work. The Contactor also placed curb & gutter on the west side of Rose this week.
Work projected for next week (5/2):
A Lamp is expected to complete the remaining concrete pavement work on the west side of Grove as well as the entire west side of Rose. Additionally repair work on the remaining brick paver driveways is anticipated to be completed next week. Parkway restoration work will resume with grading and placement of topsoil on portions of the project.
Thank you for your continued patience during the project!