The weather looks great this week. The Contractor expects to place the east side concrete pavement on Thursday. While placing concrete pavement the open single lane on Harvey will have construction vehicles and concrete trucks staged. All residents should plan on avoiding driving on the open lane Thursday. Several hours after concrete placement the contractor will come back with a pavement saw to saw the pavement joints. This work may occur later in the evening or even at night. It is extremely important to complete the pavement sawing as soon as the concrete is ready. We apologize in advance for the saw cut noise.
After the concrete pavement on the east side is set the concrete will require about a week to set, cure and gain sufficient strength. Then work will switch over the the west side.