Posted on: May 24, 2023
The lack of rain the last couple of weeks has helped keep the project work moving forward. Unfortunately, the lack of rain also has lead to an increase in the spread of construction dust that is tracked by vehicles and construction equipment within the wo...
Read on...
Central Avenue Reconstruction
Posted on: May 16, 2023
This Thursday May 18th, another water outage is expected to occur impacting Central Avenue between 47th and Burlington. A notice will be delivered to all impacted properties this afternoon. The outage is needed to adjust water infrastructure to facilitate...
Read on...
Central Avenue Reconstruction
Posted on: May 8, 2023
This week we expect the contractor will work on sewer installation on the west side of Central Avenue. We are anticipating a planned water outage on Thursday for Central Avenue residents between Burlington Avenue and 47th Street. The water outage is neede...
Read on...
Central Avenue Reconstruction
Posted on: April 28, 2023
The Contractor expects to begin work on the replacement of a Village 36” sanitary sewer that runs under 47th Street located at Fair Elms Avenue. The work will require reducing 47th Street down to one lane Monday morning. Traffic will be controll...
Read on...
Central Avenue Reconstruction
Posted on: April 14, 2023
This week the Contractor was working on the storm sewer crossing under 47th Street and on the south side of 47th Street prepping the area so they can begin the storm sewer outfall construction. The week of April 17th we expect the contractor will be insta...
Read on...
Central Avenue Reconstruction
Posted on: March 31, 2023
Earlier this afternoon a construction update was left at the front door of each home on Central Avenue within the project limits. The notice contains an update on upcoming work as well as an overall project schedule update. A copy of this notice can be vi...
Read on...
Central Avenue Reconstruction
Posted on: March 27, 2023
This week the Contractor is currently working on installing the sewer casing pipe under 47th Street (west of Commonwealth Drive). They are also installing new storm sewer on the north side of 47th Street heading east towards Central Avenue. We anticipate ...
Read on...
Central Avenue Reconstruction
Posted on: March 13, 2023
This week the contractor advised they expect to install a temporary chain link construction fence along 47th Street and on Central Avenue from 47th Street to Elm Street.
The Contractor is expected to continue to focus their efforts on the sewer work on the...
Read on...
Central Avenue Reconstruction
Posted on: March 3, 2023
The project contractor has advised the Village they will begin work on the 47th Street storm sewer crossing starting the week of 3/6. The Contractor will be working off roadway just north of 47th Street and west of Commonwealth Drive. No major work on Cen...
Read on...
Central Avenue Reconstruction
Posted on: January 11, 2023
AT&T's contractor has advised the Village they intend to complete pavement sawcutting work tomorrow (1/12) on Elm Street. The work will occur at several locations on Elm Street between Central Ave and Lawn Ave. Over the next couple of weeks t...
Read on...
Central Avenue Reconstruction
Posted on: November 21, 2022
While performing sewer replacement work earlier this morning a water service line was accidentally damaged. The water main on Central Avenue between Burlington and 47th Street had to be shutdown so the water service line could be repaired. We apologize fo...
Read on...
Central Avenue Reconstruction
Posted on: November 1, 2022
Work on the Central Avenue Reconstruction and Storm Water Improvements project is still in the early stages of construction. There are several utilities that are in the process of being relocated and have impacted the project’s schedul...
Read on...
Central Avenue Reconstruction
Posted on: September 1, 2022
Due to scheduling issues, the tree removal work discussed in the prior project update has not yet begun. Earlier this afternoon the Contractor informed the Village that they expect to begin tree removal work tomorrow on 47th Street, however the Contractor...
Read on...
Central Avenue Reconstruction
Posted on: August 17, 2022
AT&T adjustment work continues and it appears to be nearing completion. The Contractor has completed utility potholing on 47th Street and is currently working on Central Avenue to locate existing utilities.
Tree Removals to Begin Next Week
The Contracto...
Read on...
Central Avenue Reconstruction
Posted on: August 10, 2022
AT&T's contractor is continuing to work on adjusting their facilities on Central Avenue. The Village project Contractor Berger Excavating has indicated they expect to be on site Thursday with a small crew and a vactor truck doing exploratory ...
Read on...
Central Avenue Reconstruction
Posted on: July 28, 2022
AT&T's contractor continues to work on adjusting their facilities on Central Avenue. Separately, the Village was advised by the project contractor Berger Excavating that they intend to be on site doing utility potholing work next week. This w...
Read on...
Central Avenue Reconstruction
Posted on: June 14, 2022
The Central Avenue reconstruction and sewer separation project is expected to start construction this summer. An exact start date is not known at this time however it could begin as early as next month. The Village is hosting a project open house on June ...
Read on...
Central Avenue Reconstruction
Posted on: June 9, 2022
Save the date! The Village will be hosting a project open house on June 28, 2022, 5:30 pm to 7:00 pm. The event will be located in Spring Rock park at the pavilion located just west of the Elm Street park parking lot. A formal invite with additional detai...
Read on...
Central Avenue Reconstruction
Posted on: May 10, 2022
A ComEd contractor has started work installing new power poles on Central Avenue. These new poles will replace several existing power poles on Central Avenue that are in conflict with the proposed Central Avenue Improvements. Five poles on Central Avenue ...
Read on...
Central Avenue Reconstruction