News Flash

Posted on: July 30, 2021

Grand Ave project update 7/30

This week the Village's contractor continued installing new storm sewer. Nicor Gas' contractor worked on installation of new gas service lines. Next week (week of 8/2) Nicor's contractor will be working on switching over homes t...

Read on...

Grand Ave Roadway Improvements
Posted on: July 23, 2021

Grand Ave project update 7/23

This week Nicor Gas' contractor was on site working on the installation of new gas main and testing the new gas main. The Village's underground contractor also installed new storm sewer on Grand near Park Place. The week of 7-26 we antic...

Read on...

Grand Ave Roadway Improvements
Posted on: July 16, 2021

Grand Ave Project Update 07/16

This week, the contractor installed storm sewer structures at the southwest corner of Oak Lane, Linder Lane (between Linden Circle and Oak Lane) and at the intersection of Park Place and Grand Ave. Next week, NPL will be relocating gas main near the Park ...

Read on...

Grand Ave Roadway Improvements
Posted on: July 8, 2021

Storm sewer work expected to begin 7/12

The contractor has advised they expect to begin storm sewer installation on Monday July 12. We anticipate they will be working on installing the new storm sewer the entire week.

Grand Ave Roadway Improvements
Posted on: July 1, 2021

Grand Ave work to begin week of 7/6 (Tuesday)

Work on the Grand Avenue Reconstruction project to begin the week of 7/6. Expected work includes pavement saw cutting, construction material/equipment deliveries, and storm sewer installation.

Additional Info... Grand Ave Roadway Improvements
Posted on: May 10, 2021

2021 Grand Avenue Improvements Project - Public Meeting Zoom Details

The Zoom Webinar details for the 2021 Grand Avenue Improvements Project Public Meeting are below. The meeting is scheduled for Wednesday, May 12th, at 6:00 p.m. Staff will review the project scope, impacts to residents, and instructions on how to stay inf...

Read on...

Grand Ave Roadway Improvements